The HVAC project is continuing to make good progress at the Listowel Memorial Hospital.
Phase 2 of the project is nearing completion which includes the 2nd floor north wing at the hospital.
Its expected later this month when the this phase of the project will be done and which the space will be handed back to clinical.
Phase 4 of the admin area end of the project started on August 29th with an expected completion date in April 2025, continuing to build on more upgrades at the Listowel hospital.